Question
Find the sequence that minimizes the total elapsed time required to complete the following tasks on two machines:
|
Tasks: |
A |
B |
C |
D |
E |
F |
G |
H |
I |
|
Machine I: |
2 |
5 |
4 |
9 |
6 |
8 |
7 |
5 |
4 |
|
Machine II: |
6 |
8 |
7 |
4 |
3 |
9 |
3 |
8 |
11 |
Answer :